Work starts on next phase of Bolsover industrial park

3 Sep McLaren 萝莉原创 has begun phase two works at the Horizon 29 industrial and distribution park in Bolsover, Derbyshire.

Horizon 29
Horizon 29

Horizon 29 is being built by McLaren 萝莉原创 (Midlands and North) in three phases for clients BGO Wire PropCo Ltd and Equation Properties.

Once fully complete, it will span 1,150,256 sq ft and have a total of eight warehouses.

Phases 1A and 1B were completed in February this year, comprising offour warehouse units (units 1, 2, 4 and 5).

Phase 2 is the construction of two single-storey base build distribution warehouses 鈥 units 7 and 8. These will be 249,995 sq ft and 249,866 sq ft respectively, and each will include a two-storey office, with associated mechanical and electrical installations, 23 loading docks and a transport office.

McLaren 萝莉原创 is delivering earthworks, piling (both controlled modulus and vibro stone column), concrete foundations, steel framing and cladding, lift shaft and stair installations.

Related Information

All external works are also being undertaken by McLaren, including general hard standings, car-parking, landscaping, mains services and drainage.

Sustainable features will include solar PVs, air source heat pumps, enhanced cladding, LED lighting, electric vehicle charging points, and bird and bat boxes. The units are designed to achieve a BREEAM Rating of 鈥楨xcellent,鈥 with an EPC 鈥楢鈥 Rating. Phase 2 has a 49-week build programme.

Gary Cramp, managing director of McLaren 萝莉原创 (Midlands and North), said: 鈥淗orizon 29 is going to be a premier distribution centre for Derbyshire and the wider East Midlands. It provides an ideal opportunity for tenants looking for direct and easy access to the M1 north and south.

鈥淧rogressing on to Phase 2, we are building two more units at the site - and as with earlier phases 鈥 they will be highly energy efficient buildings, with the potential for the whole of the roofs to be used to gather energy from PV to not only power the units, but to put energy back into the National Grid.鈥