Wide-drum Wirtgen speeds M62 resurfacing

5 Jun 18 Tarmac’s wide road building machinery has proven itself on an M62 resurfacing project, considerably reducing the time needed to complete the job.

The wide Wirtgen enables single pass planing
The wide Wirtgen enables single pass planing

A unique 3.8-metre drum fitted to a Wirtgen W 250i enables the machine to remove around 600 tonnes of asphalt per hour 鈥 the equivalent of 30 truck-loads, which means the road is ready to be resurfaced much earlier than using the standard method, creating a longer working window.

This machine can plane one full-lane width up to 3.8-metres wide in a single pass, unlike the standard method of doing multiple passes. The planer, operating with a Volvo 8820 paver, has been used to resurface 33 lane miles of the M62 between Rothwell and Normanton (junctions 30-31).

The wide Volvo paver can lay two full width lanes of road surfacing at a time, eliminating one of the joints between the lanes, improving the durability and resilience of the pavement.

There is also an added safety benefit for staff as 50% of the reversing is eliminated.

The A-one+ joint venture was main contractor for the Highways England scheme, which involved replacing 6,143 metres of steel central reservation barrier with concrete, along with 24 new lighting columns, 38,962 metres of new road markings and 3,768 metres of renewed and improved drainage systems.

Related Information

Highways England project manager Andy Barlow said: 鈥淲e are always keen to trial new innovative technology and ways of working, particularly where it can help improve productivity, enable roadworks to be completed quicker and minimise the disruption for drivers. Utilising Tarmac鈥檚 wide paving machine on the M62 scheme was the ideal opportunity.

鈥淭his machine not only has the benefit of being capable of laying up to 1,500 tonnes of surfacing material in a single shift 鈥 around 15,625 square metres of surface 鈥 but is also able to resurface two full lanes in one go.

鈥淭his eliminates the joint between the running lanes, which would be present if we had done the more traditional method of resurfacing a single lane. As these areas are often the locations where problems with the carriageway surface occurs, this method it should hopefully increase the life of the surface.鈥

A-one+ senior project manager Linda Carr said: 鈥淲e are always looking at ways we can increase productivity to achieve our efficiency targets and the success of this whole scheme was through real partnership working, from end to end with Highways England and our supply chain, specifically Tarmac and NRP for traffic management and planing and CR Civils for drainage and civils.

鈥淯sing these two new pieces of equipment we were able to reduce the amount of closures which benefitted customers and local communities. We were also able to incorporate additional works into the scheme averting future closures.鈥

There are plans to use the larger planer and paver in the future on the motorway network.