萝莉原创

萝莉原创

22 December 2024

Related Information

Hinkley Point C now 44% costlier than original estimate

23 May 22 The expected cost of building the Hinkley Point C nuclear power station has gone up by another £3bn in the past four months and the launch date has been put back again.

The next major project milestone is the lifting of the dome on Unit 1, forecast for the second quarter of 2023
The next major project milestone is the lifting of the dome on Unit 1, forecast for the second quarter of 2023

A statement from French state energy firm 脡lectricit茅 de France, majority owner of the Hinkley Point C project, reveals that the project completion costs are now estimated in the range of 拢25bn to 拢26bn [2015 prices].

A final cost of 拢26bn would be 44% ahead of the original estimate of 拢18bn on which the business case rested.

The start of electricity generation for Unit 1 is now targeted for June 2027, the risk of further delay of the two units is assessed at 15 months, 鈥渁ssuming the absence of a new pandemic wave and no additional effects of the war in Ukraine鈥.

The previous project review, completed in January 2022 put the cost of completion at 拢22bn to 拢23bn. In September 2019 the cost was estimated at 拢21.5bn - 拢22.5bn [all at 2015 prices].

Under the terms of the contract for difference, there should be no impact for UK consumers, EDF said. The fuel prices have been fixed in advance in agreement with the UK government.

Related Information

The latest review looked only at the main aspects of the project. The schedule and cost of electromechanical works and of final testing have not been reviewed.

Explaining the cost increases, EDF said: 鈥淒uring more than two years of the Covid-19 pandemic, the project continued without stopping. This protected the integrity of the supply chain and allowed the completion of major milestones. However, people, resources and supply chain have been severely constrained and their efficiency has been restricted. In addition, the quantities of materials and engineering as well as the cost of such activities, including, in particular marine works have risen.鈥

The next major milestone is the lifting of the dome on Unit 1, forecast for the second quarter of 2023.

EDF Energy of France is developing Hinkley Point C in joint venture with China General Nuclear Power Group (CGN). Main contractor is Bylor, a joint venture of Bouygues and Laing O鈥橰ourke.

Got a story? Email news@theconstructionindex.co.uk

MPU

Click here to view latest construction news »